Ida Street Bridge Repairs

Sector Local government

Year 2025, completed

Location Mayfield NSW

Client Local council

Value $240k

Concrete remediation of the Ida Street bridge for a local council, delivered from May to July 2025 against a project ITP with hold and witness points. Keevs established the site and traffic control, removed spalled and loose concrete, cleaned exposed reinforcement and treated it with zinc-rich coating, then completed patch repairs, epoxy crack injection, joint cleaning and sealing, and void filling at the northern abutment. The works finished with a two-coat protective coating and new W-beam rail and bridge barrier.

Back to projects